Hubble works but servicing slips
The final mission to service the Hubble space telescope has slipped
deeper into next year, Nasa has announced.
Officials said
the delay would give engineers extra time to prepare a spare control unit
needed to replace one that broke on the observatory last month.
Hubble was
taken offline for four weeks by the failure but has since been re-booted using
a back-up system.
Meanwhile Nasa
said the space shuttle Endeavour would launch on 14 November to the
International Space Station.
The Endeavour
is being sent to outfit the ISS for six crew members instead of three.
The 15-day
flight will include four spacewalks to repair the station's power system and
carry equipment to sustain the astronauts.
Path to launch
It was hoped
the Hubble reserve control unit could be made ready for launch by February.
April is now the earliest date.
The US space
agency will then have to find a slot for the servicing mission in the sequence
of construction and re-supply flights already planned to go to the
International Space Station.
Evidence that
science data is flowing again on Hubble came with the release on Thursday of a
spectacular new image of a pair of interacting galaxies known as Arp 147.
Hubble's recent
woes go back to Saturday, 27 September, just weeks before the fifth and final
servicing mission was due to blast off.
Hubble's
main flight computer put the observatory's instruments in a protective safe
mode when it detected a malfunction in the telescope's Science Instrument
Command and Data Handling (SIC&DH) Unit. The anomaly was traced to a box
that formats, stores and routes data gathered by Hubble's imaging instruments.
Engineers
successfully switched Hubble over to a "B" formatter - but the
failure left the observatory with no redundant capability.
The
spare unit Nasa now intends to fly on the rescheduled servicing mission is as
old as the telescope and needs an extensive programme of testing before it is
declared flight worthy.
"Our
plan overall takes something on the order of about six-and-a-half months from
now," explained Preston Burch, Hubble Space Telescope manager at Nasa's
Goddard Space Flight Center in Maryland.
"There's
about a month or so devoted to inspecting and resolving any of the performance
issues associated with [the spare unit]; about three months for environmental
tests; and then about two to two-and-a-half months to do final testing and
shipping down to the Kennedy Space Center and getting it installed on the
orbiter.
"In
addition, there are also approximately three tools that need to be developed to
facilitate its installation on orbit."
Longer life
The
final servicing mission will be undertaken by astronauts on the Atlantis
shuttle.
The
telescope's batteries and gyroscopes, which are used to point the telescope,
are degrading and need to be replaced.
The
orbiter crew is also tasked with installing two new instruments: the Wide Field
Camera 3 (WFC3), and the Cosmic Origins Spectrograph (COS). The new instruments
will improve significantly Hubble's ability to probe distant, faint objects in
the early Universe.
The
Atlantis astronauts must also repair two instruments that have failed in recent
years - the Advanced Camera for Surveys (ACS) and the Space Telescope Imaging
Spectrograph (STIS).
If
the work is carried out successfully, it should allow Hubble to keep operating
into the next decade.